- Grading work continues this week
- Cut and fill of base material scheduled to finish up this week
- Material being pushed from the high side (east side of site) to the low side (west side of site)
- Park entry road and parking lot has been cut in and graveled
- Walking trail on west side of site complete and hydro seeded
- Walking trail to Tahoma High School from adjoining neighborhoods is in and graveled along the west side of the site (see photo)
-
- Utility trenching expected to start next week
- The site is an active construction site, authorized personnel only.
- Sign up for project eNotifications at: https://go.usa.gov/xUtm3
- Visit the Summit Park Project page for project details.
- View photos on the City’s Facebook page @maplevalleywa
For additional project information or if you have questions regarding this project, please email Greg Brown, Capital Projects Manager at greg.brown@maplevalleywa.gov.